"We Don't Have the IT Resources": What Implementation Really Requires
- Tayana Solutions
- 1 day ago
- 4 min read
The IT Resource Concern
"We don't have IT resources for AI implementation" is a common objection. Understanding actual IT requirements versus perceived needs prevents this from blocking valuable automation.
Reality: Implementation requires 5-10 hours IT support total, not dedicated staff.
What IT Actually Does
Activity 1: API Credentials (1-2 hours)
What's needed:
Create service account in ERP
Generate API credentials (key/secret or OAuth)
Provide credentials to implementation partner
Verify test environment access
IT skill level: Junior to mid-level administrator
When needed: Week 1 of implementation
Complexity: Low. Standard procedure for most ERPs.
Activity 2: Security Review (1-2 hours)
What's needed:
Review integration approach
Approve external system access
Confirm data privacy compliance
Sign off on security measures
IT skill level: IT manager or security lead
When needed: Week 1, one-time approval
Complexity: Low to moderate depending on security policies
Activity 3: Troubleshooting Support (2-4 hours total)
What's needed:
Investigate occasional connectivity issues
Verify firewall rules if needed
Check service account permissions
Assist with production deployment
IT skill level: Mid-level administrator
When needed: Sporadically during weeks 2-12
Complexity: Low. Standard troubleshooting.
Activity 4: Production Deployment Support (1-2 hours)
What's needed:
Provide production credentials
Verify production connectivity
Confirm monitoring alerts configured
Sign off on go-live
IT skill level: IT manager approval, admin execution
When needed: Week 8-10
Complexity: Low
Total IT Time Required
Discovery phase: 1 hour (explain current systems, data access)
Implementation phase: 2-3 hours (credentials, security review)
Testing phase: 1-2 hours (troubleshooting, verification)
Deployment phase: 1-2 hours (production setup)
Post-deployment: 1 hour (occasional support)
Total: 6-9 hours over 12 weeks
Average: 30-45 minutes per week
What IT Does NOT Do
NOT Required: Custom Development
Responsibility: Implementation partner handles all development
IT role: None (unless custom ERP requires API development)
NOT Required: Project Management
Responsibility: Business team (AR, AP, Controller) leads project
IT role: Supporting participant only
NOT Required: AI Configuration
Responsibility: Implementation partner configures AI platform
IT role: None
NOT Required: Ongoing Management
Responsibility: Business team monitors and refines
IT role: Minimal (occasional technical support only)
IT Resource Availability Scenarios
Scenario 1: Dedicated IT Team
Availability: IT manager + 2-3 administrators
Implementation impact: Minimal. 1-2 hours total from IT manager, 5-7 hours from administrator.
Timeline: No delay. IT can provide support when needed.
Recommendation: Standard implementation approach
Scenario 2: Outsourced IT
Availability: MSP or outsourced IT provider on retainer
Implementation impact: Low. Request 8-10 hours IT support in implementation scope.
Timeline: Coordinate timing with MSP. May add 1-2 weeks if MSP scheduling delays.
Recommendation: Notify MSP early, include in their monthly hours
Additional cost: $0 if within retainer, $800-$1,500 if billed separately
Scenario 3: Part-Time IT Person
Availability: IT person 2-3 days weekly or consultant on call
Implementation impact: Moderate. Need to coordinate availability.
Timeline: May add 2-3 weeks to accommodate IT schedule
Recommendation: Plan IT touchpoints in advance, batch requests
Scenario 4: No Dedicated IT
Availability: Controller or operations manager handles basic IT, consultant for complex needs
Implementation impact: Higher. May need outside IT consultant for specific tasks.
Timeline: Add 2-4 weeks for consultant engagement
Recommendation: Engage IT consultant for implementation support
Additional cost: $1,500-$3,000 for consultant time
Managed Service Alternatives
Implementation Partner Handles IT Coordination
Approach: Partner coordinates directly with your IT provider (internal or external)
Your role: Introduction and approval only
Benefit: Minimal business team involvement in IT coordination
Cost: Included in standard implementation
Fully Managed Implementation
Approach: Partner handles all technical aspects including IT coordination
Your role: Business process definition only
Benefit: Zero IT coordination burden
Cost: Standard implementation pricing
Suitable for: Companies with very limited IT or IT resistance
Common IT Concerns and Responses
Concern 1: "We don't allow external system access"
Response: AI platforms don't require direct ERP access. API calls go through standard authentication. Same security model as mobile apps or other integrations.
Solution: Security review confirms standard integration approach
Concern 2: "We're too busy for new projects"
Response: Total IT time is 6-9 hours over 12 weeks (average 30-45 minutes weekly). Can be scheduled around other priorities.
Solution: Batch IT requests, provide advance notice, schedule at IT convenience
Concern 3: "We don't understand AI technology"
Response: IT doesn't need AI expertise. Implementation partner handles AI configuration. IT provides standard ERP access only.
Solution: Clear scope documentation showing IT tasks are standard ERP administration
Concern 4: "What if something breaks?"
Response: AI accesses ERP read-only mostly (writes notes/tasks only). Cannot modify customer data, transactions, or configurations. ERP integrity unaffected.
Solution: Technical documentation showing safe integration approach
IT Liaison Role
Recommended Approach
Identify one IT liaison: Person who coordinates IT support during implementation
Time commitment: 1-2 hours monthly for 3 months
Responsibilities:
Attend kickoff meeting (1 hour)
Provide API credentials when ready
Troubleshoot connectivity if issues arise
Approve production deployment
Suitable person:
ERP administrator
IT manager
MSP account manager
Technology-comfortable operations person
NOT required:
Deep AI knowledge
Programming skills
Dedicated project time
When IT Effort Increases
Scenario: Custom ERP with No API
Additional IT work:
API development: 40-80 hours
Or database integration setup: 20-40 hours
Timeline impact: +4-8 weeks
Cost impact: +$15,000-$40,000
Alternative: ERP upgrade or standardize before AI implementation
Scenario: Highly Restricted Security Environment
Additional IT work:
Extended security reviews: 5-10 hours
Custom security configuration: 5-10 hours
Penetration testing: 10-20 hours
Timeline impact: +2-4 weeks
Cost impact: +$5,000-$15,000
Industries affected: Healthcare, financial services, government contractors
The Reality
AI implementation requires 5-10 hours total IT support over 12 weeks. Average 30-45 minutes weekly.
IT provides: API credentials, security approval, occasional troubleshooting.
IT does NOT: Custom development, project management, AI configuration, ongoing management.
Limited IT availability adds 2-4 weeks timeline but doesn't prevent implementation. Outsourced IT or consultant alternatives available.
"We don't have IT resources" typically means "We don't understand minimal IT requirements." Actual needs are modest and manageable.
About the Author: This content is published by ERP AI Agent.